Updated schedule for Ministry of Transportation’s East Shuswap temporary road construction works:

Week of Oct. 19th – Establish top cut and contouring the slope profile. Locating utilities with hydro vac truck. Begin asphalt removal.
Week of Oct. 26th – Bank insulation work and building up temporary roadway. Complete asphalt removal.
Week of Nov. 2nd – Paving and site clean up.

Local residential traffic will be impacted during asphalt removal and road building activities. Some delays are expected.
Construction signage and flaggers will maintain traffic through the site. With a focus on maintaining morning and afternoon commutes to work/school.