Both seasonal North and East ARDA raw water systems received major repairs over the winter and are running.
North ARDA system
North ARDA irrigation system repairs included the installation of recast sedimentation pond walls and baffles. The system is operational.
East ARDA system
A new pump and flow meters have been installed and the system is currently operating manually just as last year.
Public Works is waiting for a new control panel to be installed that will allow for variable pump speeds and remote flow monitoring alarms. Switch over to the new control panel is expected in June with no system shutdowns. Water users are asked to continue to support TteS water operators by having as many lines out as possible to accommodate the system pressure needs.
For any service questions or to report water breaks or leaks in the water lines, please contact:
Tk’emlúps te Secwépemc
Public Works Department
(250) 318-6400